Calvert Vaux Park Public Restroom Building and Maintenance Facility Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a public restroom building and maintenance facility in Calvert Vaux Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2011
Projected Completion Date:
August 2014
Completion Date:
January 2018
Procurement
Start Date: January 2018
Projected Completion Date:
October 2018
Completion
Date:
July 2019
Construction
Start Date: December 2019
Projected Completion Date:
May 2021
Completion Date: March 2023
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Calvert Vaux Park, Brooklyn
Shore Parkway near Bay 48th Street
Community Board: 13
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project