Riverside Oval and Verdi Square Water Service Installation

  • Design
    30% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will provide water service to Riverside Oval and Verdi Square.

Project Notes

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

Project Timeline

Design

Assigned & Start Date: January 2024
Projected Completion Date: July 2025

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • Borough President
  • City Council

Locations

  • Verdi Square, Manhattan
    Broadway, Amsterdam Avenue & West 73 Street
    Community Board: 07
  • DOT (Non-Parks) Property in Manhattan
 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024