Aqueduct Walk Retaining Wall Reconstruction
-
80% complete
-
0% complete
-
0% complete
This project will reconstruct the retaining wall at Aqueduct Walk.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2021
Projected Completion Date:
December 2022
Adjusted Completion Date:
December 2024
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Aqueduct Walk, Bronx
between West 190th Street and West Fordham Road
Community Board: 05, 07
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024