Flushing Fields Leonardo Ingravallo Playground Reconstruction

  • Design
    90% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct Leonardo Ingravallo Playground in Flushing Fields.

Project Notes

Project Update: All contract documents are now in final review to complete the design process.

Project Timeline

Design

Assigned & Start Date: May 2023
Projected Completion Date: October 2024

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: City Council

Location

Flushing Fields, Queens
149th Street and 25th Avenue
Community Board: 07

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024