Flushing Meadows Corona Park Pool Locker Room Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the men's locker room in the FMCP pool facility into a family changing room.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2016
Projected Completion Date:
March 2016
Completion Date:
October 2016
Procurement
Start Date: April 2016
Projected Completion Date:
September 2016
Completion
Date:
October 2016
Construction
Start Date: October 2016
Projected Completion Date:
May 2017
Completion Date: October 2017