Allen and Pike Street Malls Reconstruction Phase 2

  • Design
    30% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the Allen and Pike Street Malls.

Project Notes

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

Project Timeline

Design

Assigned & Start Date: October 2023
Projected Completion Date: April 2025

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: Mayoral

Location

Allen Street Malls, Manhattan
Allen Street and Pike Street between Hester Street and Madison Street
Community Board: 03

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024