Allen and Pike Street Malls Reconstruction Phase 2
-
30% complete
-
0% complete
-
0% complete
This project will reconstruct the Allen and Pike Street Malls.
Project Notes
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.
Project Timeline
Design
Assigned & Start Date: October 2023
Projected Completion Date:
April 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Allen Street Malls, Manhattan
Allen Street and Pike Street between Hester Street and Madison Street
Community Board: 03
Project Staff
Project Liaison: Steve Simon