Allen and Pike Street Malls Reconstruction Phase 2
-
35% complete
-
0% complete
-
0% complete
This project will reconstruct the Allen and Pike Street Malls.
Project Notes
Project Update: The schematic design for this project has been approved. Parks is now developing the documents required to build this project.
Project Timeline
Design
Assigned & Start Date: October 2023
Projected Completion Date:
April 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Allen Street Malls, Manhattan
Allen Street and Pike Street between Hester Street and Madison Street
Community Board: 03
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025