Kissena Park Greenway Construction

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct a greenway at Kissena Park.

Project Notes

Project Update: Parks has reviewed stakeholder feedback and the scope of work for this project, and is now developing the design for the site.

Project Timeline

Design

Assigned & Start Date: December 2024
Projected Completion Date: December 2026

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • City Council
  • Mayoral

Location

Between Main Street and Kissena Blvd and Kissena Blvd and 164th Street and 164th Street and Fresh Meadow Lane

 

Project Staff

Contact NYC Parks about this project

Last updated: 03/28/2025