Kissena Park Greenway Construction
-
5% complete
-
0% complete
-
0% complete
This project will construct a greenway at Kissena Park.
Project Notes
Project Update: Parks has reviewed stakeholder feedback and the scope of work for this project, and is now developing the design for the site.
Project Timeline
Design
Assigned & Start Date: December 2024
Projected Completion Date:
December 2026
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Between Main Street and Kissena Blvd and Kissena Blvd and 164th Street and 164th Street and Fresh Meadow Lane
Project Staff
Contact NYC Parks about this projectLast updated: 03/28/2025