Flushing Meadows Corona Park Destination Greenways Meadow Lake Segment Construction
-
30% complete
-
0% complete
-
0% complete
This project will construct a greenway at Flushing Meadows Corona Park by Meadow Lake Creek.
Project Notes
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.
Project Timeline
Design
Assigned & Start Date: November 2023
Projected Completion Date:
January 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Flushing Meadows Corona Park, Queens
The pathway around Meadow Lake in Flushing Meadows Corona Park between Grand Central Parkway, Van Wyck Expressway, 69th Road and the Long Island Expressway
Community Board: 03, 04, 06, 07, 08
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024