Lew Fidler Park Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct Lew Fidler Park, including a new playground with play equipment, swings, spray shower area, hillside slide and a picnic area in Marine Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2011
Projected Completion Date: December 2014
Completion Date: August 2017

Procurement

Start Date: August 2017
Projected Completion Date: May 2018
Completion Date: July 2018

Construction

Start Date: November 2018
Projected Completion Date: May 2020
Completion Date: March 2021

Understand how we build parks.

Funding

Total Funding: $5,624,000
Funding Sources:
  • City Council
  • Mayoral

Location

Marine Park, Brooklyn
Southeast corner of Brigham Street and Emmons Avenue
Community Board: 15, 18

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project