Leif Ericson Park Greenway Construction

  • Design
    35% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct a greenway at Leif Ericson Park.

Project Notes

Project Update: The schematic design for this project has been approved. Parks is now developing the documents required to build this project.

Project Timeline

Design

Assigned & Start Date: October 2023
Projected Completion Date: April 2025

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Sources:
  • Borough President
  • Mayoral

Location

Leif Ericson Park, Brooklyn
67th Street, 66th Street between 2nd Avenue and 7th Avenue
Community Board: 10

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025