Shore Park Parkway Promenade and 4th Avenue Entrance Greenway Reconstruction
-
30% complete
-
0% complete
-
0% complete
This project will reconstruct the promenade, greenway and 4th Avenue greenway entrance.
Project Notes
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.
Project Timeline
Design
Assigned & Start Date: November 2023
Projected Completion Date:
May 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- Mayoral
Location
Shore Park and Parkway, Brooklyn
Shore Parkway Greenway West Between Bay Ridge Avenue and 4th Avenue Greenway Entrance
Community Board: 10
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024