Shore Park Parkway Promenade and 4th Avenue Entrance Greenway Reconstruction
-
35% complete
-
0% complete
-
0% complete
This project will reconstruct the promenade, greenway and 4th Avenue greenway entrance.
Project Notes
Project Update: The schematic design for this project has been approved. Parks is now developing the documents required to build this project.
Project Timeline
Design
Assigned & Start Date: November 2023
Projected Completion Date:
May 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- Mayoral
Location
Shore Park and Parkway, Brooklyn
Shore Parkway Greenway West Between Bay Ridge Avenue and 4th Avenue Greenway Entrance
Community Board: 10
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025