Jennie Jerome Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct Jennie Jerome Playground.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2022
Projected Completion Date: September 2023
Completion Date: October 2023

Procurement

Start Date: October 2023
Projected Completion Date: October 2024
Completion Date: December 2024

Construction

Start Date: November 2024
Projected Completion Date: November 2025

Understand how we build parks.

Funding

Total Funding: $4,111,000
Funding Source: Mayoral

Location

Jennie Jerome Playground, Bronx
Jerome Avenue and East 174th Street
Community Board: 05

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 01/17/2025