Wingate Park & Glenwood Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This multisite contract will reconstruct a portion of the playground at Wingate Park and a portion of the playground at Glenwood Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2012
Projected Completion Date:
April 2012
Completion Date:
September 2013
Procurement
Start Date: September 2013
Projected Completion Date:
May 2014
Completion
Date:
July 2014
Construction
Start Date: September 2014
Projected Completion Date:
September 2015
Completion Date: May 2016
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Glenwood Playground, Brooklyn
Ralph Av and Farragut Rd
Community Board: 18 -
Wingate Park, Brooklyn
S E Corner Brooklyn Av and Rutl& Rd
Community Board: 09
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025