Frank D. O'Connor Playground Reconstruction

  • Design
    100% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct Frank D. O'Connor Playground.

Project Notes

Project Update: Design is complete and permitting and legal review of the contract are in progress.

Project Timeline

Design

Assigned & Start Date: May 2023
Projected Completion Date: August 2024
Completion Date: August 2024

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Frank D. O'Connor Playground, Queens
Broadway and Woodside between 77th and 79th Street
Community Board: 04

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024