St. James Recreation Center HVAC and Boiler Emergency Reconstruction (Hurricane Ida)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the boiler, heating and air conditioning systems that were damaged by Hurricane Ida at St. James Recreation Center.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2022
Projected Completion Date:
October 2022
Completion Date:
August 2022
Procurement
Start Date: August 2022
Projected Completion Date:
May 2023
Completion
Date:
July 2023
Construction
Start Date: March 2023
Projected Completion Date:
March 2024
Completion Date: February 2024
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
St. James Park, Bronx
Jerome Avenue and East 193rd Street
Community Board: 07
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 01/17/2025