St. James Recreation Center HVAC and Boiler Emergency Reconstruction (Hurricane Ida)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the boiler, heating and air conditioning systems that were damaged by Hurricane Ida at St. James Recreation Center.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2022
Projected Completion Date: October 2022
Completion Date: August 2022

Procurement

Start Date: August 2022
Projected Completion Date: May 2023
Completion Date: July 2023

Construction

Start Date: March 2023
Projected Completion Date: March 2024
Completion Date: January 2024

Understand how we build parks.

Funding

Total Funding: $1,533,000
Funding Source: Mayoral

Location

St. James Park, Bronx
Jerome Avenue and East 193rd Street
Community Board: 07

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 10/11/2024