Dyker Beach Park Paths and Brizzi Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Brizzi Playground and the paths adjacent to Ben Vitale Fields in Dyker Beach Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2010
Projected Completion Date: April 2012
Completion Date: July 2012

Procurement

Start Date: July 2012
Projected Completion Date: April 2013
Completion Date: October 2013

Construction

Start Date: November 2013
Projected Completion Date: November 2014
Completion Date: November 2014

Understand how we build parks.

Funding

Total Funding: $874,000
Funding Sources:
  • Borough President
  • City Council

Locations

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025