Dyker Beach Park Paths and Brizzi Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Brizzi Playground and the paths adjacent to Ben Vitale Fields in Dyker Beach Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2010
Projected Completion Date:
April 2012
Completion Date:
July 2012
Procurement
Start Date: July 2012
Projected Completion Date:
April 2013
Completion
Date:
October 2013
Construction
Start Date: November 2013
Projected Completion Date:
November 2014
Completion Date: November 2014
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Locations
-
Brizzi Playground, Brooklyn
10 Ave., New Utrecht Ave. bet. 43 St. and 42 St.
Community Board: 12 -
Dyker Beach Park, Brooklyn
Cropsey & Bay 8
Community Board: 10
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025