Cooper Park Dog Run Construction and Athletic Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the basketball, handball and beach volleyball courts, and construct a dog run in Cooper Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2012
Projected Completion Date: November 2013
Completion Date: February 2014

Procurement

Start Date: February 2014
Projected Completion Date: November 2014
Completion Date: February 2015

Construction

Start Date: April 2015
Projected Completion Date: April 2016
Completion Date: December 2015

Understand how we build parks.

Funding

Total Funding: $2,458,000
Funding Sources:
  • City Council
  • State

Location

Cooper Park, Brooklyn
Maspeth Avenue, Morgan Avenue, Olive Street, Sharon Street
Community Board: 01

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project