Marcus Garvey Park Pelham Fritz Recreation Center Roof Reconstruction
-
30% complete
-
0% complete
-
0% complete
This project will reconstruct the roof at Pelham Fritz Recreation Center in Marcus Garvey Park.
Project Notes
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.
Project Timeline
Design
Assigned & Start Date: October 2022
Projected Completion Date:
December 2023
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Marcus Garvey Park, Manhattan
18 Mount Morris Park West
Community Board: 11
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024