Powell Park Adult Fitness Area Construction and Athletic Court Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the basketball and handball courts, and construct an adult fitness area in Powell Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2011
Projected Completion Date: November 2012
Completion Date: September 2013

Procurement

Start Date: September 2013
Projected Completion Date: June 2014
Completion Date: March 2015

Construction

Start Date: May 2015
Projected Completion Date: May 2016
Completion Date: October 2016

Understand how we build parks.

Funding

Total Funding: $2,453,000
Funding Sources:
  • City Council
  • Mayoral

Location

Powell Playground, Brooklyn
Powell Street between Pitkin and Glenmore Avenues, Brooklyn
Community Board: 16

 