Belt Parkway Restoration and Tree Replacement, Phase IV

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will plant replacement trees and restore native species habitat within forested natural areas adjacent to the Belt Parkway.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2022
Projected Completion Date: April 2023
Completion Date: September 2023

Procurement

Start Date: September 2023
Projected Completion Date: September 2024
Adjusted Completion Date: January 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

North of Belt Parkway between Paerdegat Basin and Spring Creek

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024