Belt Parkway Restoration and Tree Replacement, Phase IV
-
100% complete
-
85% complete
-
0% complete
This project will plant replacement trees and restore native species habitat within forested natural areas adjacent to the Belt Parkway.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2022
Projected Completion Date:
April 2023
Completion Date:
September 2023
Procurement
Start Date: September 2023
Projected Completion Date:
September 2024
Adjusted Completion
Date:
January 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
North of Belt Parkway between Paerdegat Basin and Spring Creek
Project Staff
Contact NYC Parks about this projectLast updated: 11/22/2024