Pelham Bay Park Forest Tree Replacement, Phase II
-
100% complete
-
85% complete
-
0% complete
This project will plant replacement trees and restore native species habitat within forested natural areas in Pelham Bay Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2022
Projected Completion Date:
March 2023
Completion Date:
March 2023
Procurement
Start Date: March 2023
Projected Completion Date:
March 2024
Adjusted Completion
Date:
December 2024
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Pelham Bay Park, Bronx
East of Bruckner Blvd between Watt Ave and Bronx and Pelham Parkway
Community Board: 10, 12
Project Staff
Contact NYC Parks about this projectLast updated: 11/22/2024