Cunningham Park Lower Redwood Playground Spray Shower Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the spray shower area at Lower Redwood Playground in Cunningham Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2022
Projected Completion Date: November 2022
Completion Date: September 2022

Procurement

Start Date: September 2022
Projected Completion Date: June 2023
Completion Date: August 2023

Construction

Start Date: October 2023
Projected Completion Date: July 2024
Completion Date: December 2023

Understand how we build parks.

Funding

Total Funding: Less than $1 million

Location

Cunningham Park, Queens
East side of Cunningham Park at 193rd Street and Aberdeen Road.
Community Board: 08

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024