Cunningham Park Lower Redwood Playground Spray Shower Area Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the spray shower area at Lower Redwood Playground in Cunningham Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2022
Projected Completion Date:
November 2022
Completion Date:
September 2022
Procurement
Start Date: September 2022
Projected Completion Date:
June 2023
Completion
Date:
August 2023
Construction
Start Date: October 2023
Projected Completion Date:
July 2024
Completion Date: December 2023
Understand how we build parks.
Funding
Location
Cunningham Park, Queens
East side of Cunningham Park at 193rd Street and Aberdeen Road.
Community Board: 08
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024