Citywide Invasive Species Removal
-
100% complete
-
100% complete
-
22% complete
This project will remove invasive species Citywide.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2022
Projected Completion Date:
December 2022
Completion Date:
May 2022
Procurement
Start Date:
Completion
Date:
May 2024
Construction
Start Date: May 2024
Projected Completion Date:
May 2029
Understand how we build parks.
Funding
Last updated: 11/22/2024