Coffey Park Pathway and Barbecue Area Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the paths in Coffey Park and formalize the central plaza area. The project will also provide larger planted areas for existing trees and a formal, ADA-accessible BBQ area.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2010
Projected Completion Date:
March 2013
Completion Date:
March 2013
Procurement
Start Date: March 2013
Projected Completion Date:
December 2013
Completion
Date:
February 2014
Construction
Start Date: April 2014
Projected Completion Date:
April 2015
Completion Date: June 2015
Understand how we build parks.
Funding
Funding Source: City Council
Location
Coffey Park, Brooklyn
Verona Street, King Street, Richards Street, Dwight Street
Community Board: 06
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024