Coffey Park Pathway and Barbecue Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the paths in Coffey Park and formalize the central plaza area. The project will also provide larger planted areas for existing trees and a formal, ADA-accessible BBQ area.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2010
Projected Completion Date: March 2013
Completion Date: March 2013

Procurement

Start Date: March 2013
Projected Completion Date: December 2013
Completion Date: February 2014

Construction

Start Date: April 2014
Projected Completion Date: April 2015
Completion Date: June 2015

Understand how we build parks.

Funding

Total Funding: $1,504,000
Funding Source: City Council

Location

Coffey Park, Brooklyn
Verona Street, King Street, Richards Street, Dwight Street
Community Board: 06

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024