Crispus Attucks Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground, handball courts, basketball courts, and entry plaza at Crispus Attucks Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2012
Projected Completion Date: December 2012
Completion Date: August 2014

Procurement

Start Date: August 2014
Projected Completion Date: May 2015
Completion Date: July 2015

Construction

Start Date: October 2015
Projected Completion Date: January 2017
Completion Date: April 2017

Understand how we build parks.

Funding

Total Funding: $1,595,000
Funding Source: City Council

Location

Crispus Attucks Playground, Brooklyn
Classon Avenue between Fulton Street and Lefferts Place
Community Board: 02

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024