Crispus Attucks Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the playground, handball courts, basketball courts, and entry plaza at Crispus Attucks Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2012
Projected Completion Date:
December 2012
Completion Date:
August 2014
Procurement
Start Date: August 2014
Projected Completion Date:
May 2015
Completion
Date:
July 2015
Construction
Start Date: October 2015
Projected Completion Date:
January 2017
Completion Date: April 2017
Understand how we build parks.
Funding
Funding Source: City Council
Location
Crispus Attucks Playground, Brooklyn
Classon Avenue between Fulton Street and Lefferts Place
Community Board: 02
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025