Freshkills Park Owl Hollow Fields Lawn Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct a portion of the lawn at Owl Hollow Fields in Freshkills Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2015
Projected Completion Date: October 2015
Completion Date: September 2015

Procurement

Start Date: November 2015
Projected Completion Date: April 2016
Completion Date: November 2015

Construction

Start Date: April 2016
Projected Completion Date: August 2016
Completion Date: November 2016

Understand how we build parks.

Funding

Total Funding: $35,000
Funding Source: Mayoral

Location

Freshkills Park, Staten Island

 