Project Timeline
Design
Assigned & Start Date: July 2015
Projected Completion Date:
October 2015
Completion Date:
September 2015
Procurement
Start Date: November 2015
Projected Completion Date:
April 2016
Completion
Date:
November 2015
Construction
Start Date: April 2016
Projected Completion Date:
August 2016
Completion Date: November 2016