Old Stone House Addition Construction
-
80% complete
-
0% complete
-
0% complete
This project will construct an addition to the Old Stone House.
Project Notes
Project Update: Parks staff members are reviewing construction documents for this project.
Project Timeline
Design
Assigned & Start Date: May 2023
Projected Completion Date:
November 2024
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Washington Park, Brooklyn
5th Avenue between 3rd and 4th Street
Community Board: 06
Project Staff
Project Liaison: Davey Ives