Paerdegat Park Basketball Court Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will remove and reset the granite block sidewalks; install new security lighting on the basketball court, playground, and around the public restroom building; and reconstruct the basketball court and plant surrounding lawn areas to prevent erosion. In addition, this project will install safety surface at the play area, reconstruct the tot area, and reconstruct the handball walls.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2011
Projected Completion Date:
June 2012
Completion Date:
February 2013
Procurement
Start Date: February 2013
Projected Completion Date:
November 2013
Completion
Date:
October 2013
Construction
Start Date: March 2014
Projected Completion Date:
March 2015
Completion Date: March 2015
Understand how we build parks.
Funding
Funding Source: City Council
Location
Paerdegat Park, Brooklyn
East 40th Street, Foster Avenue, Albany Avenue, and Farragut Road
Community Board: 17
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025