Clove Lakes Parking Lot Green Infrastructure Construction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will install green infrastructure within the parking lot at Clove Lakes Park.

Project Notes

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2022
Projected Completion Date: June 2023
Completion Date: November 2023

Procurement

Start Date: November 2023
Projected Completion Date: November 2024

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Clove Lakes Park, Staten Island
Martling Avenue and Clove Road
Community Board: 01

 

Project Staff

Contact NYC Parks about this project

Last updated: 01/17/2025