Clove Lakes Parking Lot Green Infrastructure Construction
-
100% complete
-
40% complete
-
0% complete
This project will install green infrastructure within the parking lot at Clove Lakes Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2022
Projected Completion Date:
June 2023
Completion Date:
November 2023
Procurement
Start Date: November 2023
Projected Completion Date:
November 2024
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Clove Lakes Park, Staten Island
Martling Avenue and Clove Road
Community Board: 01
Project Staff
Contact NYC Parks about this projectLast updated: 11/22/2024