Conference House Park Lenape Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Lenape Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2015
Projected Completion Date: September 2015
Completion Date: September 2015

Procurement

Start Date: November 2015
Projected Completion Date: April 2016
Completion Date: November 2015

Construction

Start Date: May 2016
Projected Completion Date: October 2016
Completion Date: December 2016

Understand how we build parks.

Funding

Total Funding: $471,000
Funding Source: City Council

Location

Conference House Park, Staten Island

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 01/17/2025