Crotona Park Green Infrastructure Construction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will install green infrastructure within Crotona Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2022
Projected Completion Date: July 2023
Completion Date: June 2023

Procurement

Start Date: June 2023
Projected Completion Date: June 2024
Adjusted Completion Date: October 2024

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

Crotona Park, Bronx
North of Claremont Pkwy and Fulton Ave Intersection
Community Board: 03

 

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024