Berry Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    6% complete

This project will reconstruct Berry Playground.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2022
Projected Completion Date: June 2023
Completion Date: July 2023

Procurement

Start Date: July 2023
Projected Completion Date: July 2024
Completion Date: November 2024

Construction

Start Date: December 2024
Projected Completion Date: December 2025

Understand how we build parks.

Funding

Total Funding: $3,500,000
Funding Source: Mayoral

Location

Berry Playground, Brooklyn
South 3rd Street, Berry Street and Bedford Avenue
Community Board: 01

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025