Berry Playground Reconstruction
-
100% complete
-
100% complete
-
6% complete
This project will reconstruct Berry Playground.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2022
Projected Completion Date:
June 2023
Completion Date:
July 2023
Procurement
Start Date: July 2023
Projected Completion Date:
July 2024
Completion
Date:
November 2024
Construction
Start Date: December 2024
Projected Completion Date:
December 2025
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Berry Playground, Brooklyn
South 3rd Street, Berry Street and Bedford Avenue
Community Board: 01
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025