Fort Totten Park Chapel and Commander's House Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the steeple spire and bell tower at the Chapel and reconstruct the roof and exterior woodwork at the Commander's House at Fort Totten.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2011
Projected Completion Date: May 2013
Completion Date: September 2015

Procurement

Start Date: September 2015
Projected Completion Date: June 2016
Completion Date: June 2017

Construction

Start Date: September 2017
Projected Completion Date: March 2019
Completion Date: March 2021

Understand how we build parks.

Funding

Total Funding: $5,327,000
Funding Source: Mayoral

Location

Fort Totten Park, Queens
Chapel at 423 Abbot Road, Commander's House at 422A Weaver Avenue
Community Board: 07

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024