Broad Channel American Park Parking Lot and Shad Creek Road Reconstruction

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the parking lot at Broad Channel American Park.

Project Notes

Project Update: Parks has reviewed stakeholder feedback and the scope of work for this project, and is now developing the design for the site.

Project Timeline

Design

Assigned & Start Date: May 2024
Projected Completion Date: November 2025

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • City Council
  • Mayoral

Location

Broad Channel American Park, Queens
parking lot of Broad Channel American Park, along with Shad Creek Road and the parking lot entrance road
Community Board: 14

 

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024