Old Howard Beach Shoreline Restoration

  • Design
    30% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will restore shoreline areas in Old Howard Beach.

Project Notes

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

Project Timeline

Design

Assigned & Start Date: June 2024
Projected Completion Date: December 2025

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

Bayview Avenue and Broadway near 102nd Street

 

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024