Crotona Park Tree Planting

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    1% complete

This project will plant trees in Crotona Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2021
Projected Completion Date: February 2022
Completion Date: March 2022

Procurement

Start Date: March 2022
Projected Completion Date: December 2022
Completion Date: June 2024

Construction

Start Date: September 2024
Projected Completion Date: June 2025

Understand how we build parks.

Funding

Total Funding: $200,000
Funding Source: Mayoral