Conference House Park Timber Barrier Rail Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct timber barrier rail damaged from Hurricane Sandy at Conference House Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2015
Projected Completion Date:
September 2015
Completion Date:
August 2015
Procurement
Start Date: February 2016
Projected Completion Date:
July 2016
Completion
Date:
February 2016
Construction
Start Date: May 2016
Projected Completion Date:
August 2016
Completion Date: December 2016
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- Federal
Location
Conference House Park, Staten Island
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 11/22/2024