Chief Dennis L. Devlin Park Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the passive seating and planting, construction of sidewalk, fencing, painted games and a spray shower at Chief Dennis L. Devlin Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2022
Projected Completion Date: March 2023
Completion Date: June 2023

Procurement

Start Date: June 2023
Projected Completion Date: June 2024
Adjusted Completion Date: February 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

Chief Dennis L. Devlin Park, Bronx
Ellis Avenue, Olmstead Avenue, and Cross Bronx Service Road North
Community Board: 09

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024