Chief Dennis L. Devlin Park Reconstruction
-
100% complete
-
60% complete
-
0% complete
This project will reconstruct the passive seating and planting, construction of sidewalk, fencing, painted games and a spray shower at Chief Dennis L. Devlin Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2022
Projected Completion Date:
March 2023
Completion Date:
June 2023
Procurement
Start Date: June 2023
Projected Completion Date:
June 2024
Adjusted Completion
Date:
February 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Chief Dennis L. Devlin Park, Bronx
Ellis Avenue, Olmstead Avenue, and Cross Bronx Service Road North
Community Board: 09
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024