Poe Park Plaza and Playground Reconstruction

  • Design
    50% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the plaza and playground in Poe Park.

Project Notes

Project Update: Parks is continuing to develop the documents to build this project.

Project Timeline

Design

Assigned & Start Date: February 2024
Projected Completion Date: August 2025

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Sources:
  • City Council
  • Mayoral

Location

Poe Park, Bronx
East 192nd Street, Grand Concourse, and East Kingsbridge Road
Community Board: 07

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 02/21/2025