Anibal Aviles Playground Reconstruction
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct Anibal Aviles Playground.
Project Notes
Project Update: A date has been set for construction to begin.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2022
Projected Completion Date:
April 2023
Completion Date:
June 2023
Procurement
Start Date: June 2023
Projected Completion Date:
June 2024
Completion
Date:
January 2025
Construction
Start Date: February 2025
Projected Completion Date:
February 2026
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Anibal Aviles Playground, Manhattan
West 108th Street between Columbus Avenue and Amsterdam Avenue
Community Board: 07
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 02/21/2025