Jerome Playground Reconstruction
-
100% complete
-
5% complete
-
0% complete
This project will reconstruct the basketball courts, playground, and track and field in Jerome Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2022
Projected Completion Date:
June 2023
Completion Date:
July 2023
Procurement
Start Date: July 2023
Projected Completion Date:
July 2024
Adjusted Completion
Date:
March 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Jerome Playground, Brooklyn
Wortman Avenue & Warwick Street
Community Board: 05
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024