Flushing Meadows Corona Park Aquatic Center Pool Floor Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the pool floor at the Aquatic Center in Flushing Meadows Corona Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2021
Projected Completion Date:
February 2022
Completion Date:
February 2022
Procurement
Start Date: February 2022
Projected Completion Date:
November 2022
Completion
Date:
June 2022
Construction
Start Date: September 2022
Projected Completion Date:
January 2023
Completion Date: February 2023
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Flushing Meadows Corona Park, Queens
131-04 Meridian Road
Community Board: 03, 04, 06, 07, 08
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024