Flushing Meadows Corona Park Aquatic Center Pool Floor Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the pool floor at the Aquatic Center in Flushing Meadows Corona Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2021
Projected Completion Date: February 2022
Completion Date: February 2022

Procurement

Start Date: February 2022
Projected Completion Date: November 2022
Completion Date: June 2022

Construction

Start Date: September 2022
Projected Completion Date: January 2023
Completion Date: February 2023

Understand how we build parks.

Funding

Total Funding: $1,000,000
Funding Source: Mayoral

Location

Flushing Meadows Corona Park, Queens
131-04 Meridian Road
Community Board: 03, 04, 06, 07, 08

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024