Evergreen Park Playground and Spray Shower Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will demolish the bocce and shuffleboard courts, install play equipment, and reconstruct the spray shower at Evergreen Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2012
Projected Completion Date: February 2013
Completion Date: December 2013

Procurement

Start Date: December 2013
Projected Completion Date: September 2014
Completion Date: January 2015

Construction

Start Date: March 2015
Projected Completion Date: March 2016
Completion Date: June 2016

Understand how we build parks.

Funding

Total Funding: $938,000
Funding Source: City Council

Location

Evergreen Park, Queens
Saint Felix Avenue between 60th Street and 60th Lane, Queens
Community Board: 05

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025