Horseshoe Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    6% complete

This project will reconstruct Horseshoe Playground.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2022
Projected Completion Date: February 2023
Completion Date: October 2023

Procurement

Start Date: October 2023
Projected Completion Date: October 2024
Completion Date: January 2025

Construction

Start Date: February 2025
Projected Completion Date: February 2026

Understand how we build parks.

Funding

Total Funding: $3,463,000
Funding Sources:
  • City Council
  • Mayoral

Location

Horseshoe Playground, Bronx
Rogers Place, Hall Place, and E 165th Street
Community Board: 02

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 03/28/2025