Lt. Lia Playground Reconstruction
-
100% complete
-
5% complete
-
0% complete
This project will reconstruct Lt. Lia Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2022
Projected Completion Date:
June 2023
Completion Date:
November 2023
Procurement
Start Date: November 2023
Projected Completion Date:
November 2024
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Lt. Lia Playground, Staten Island
Wall Street between Belmont Place and St. Marks Place
Community Board: 01
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 11/22/2024