Greenbelt Recreation Center Basketball Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the basketball courts at the Greenbelt Recreation Center.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2022
Projected Completion Date: June 2023
Completion Date: July 2023

Procurement

Start Date: July 2023
Projected Completion Date: July 2024
Completion Date: November 2024

Construction

Start Date: April 2025
Projected Completion Date: March 2026

Understand how we build parks.

Funding

Total Funding: $2,500,000
Funding Source: City Council

Location

Blood Root Valley, Staten Island
501 Brielle Avenue
Community Board: 02

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 01/17/2025