Alice Austen Park Buono Beach Paths and Rails Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct timber barrier rail and paths damaged from Hurricane Sandy and install new curbs at Buono Beach in Alice Austen Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2014
Projected Completion Date:
March 2015
Completion Date:
February 2015
Procurement
Start Date: July 2015
Projected Completion Date:
December 2015
Completion
Date:
July 2015
Construction
Start Date: April 2016
Projected Completion Date:
July 2016
Completion Date: July 2016