Alice Austen Park Buono Beach Paths and Rails Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct timber barrier rail and paths damaged from Hurricane Sandy and install new curbs at Buono Beach in Alice Austen Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2014
Projected Completion Date: March 2015
Completion Date: February 2015

Procurement

Start Date: July 2015
Projected Completion Date: December 2015
Completion Date: July 2015

Construction

Start Date: April 2016
Projected Completion Date: July 2016
Completion Date: July 2016

Understand how we build parks.

Funding

Total Funding: $130,000
Funding Sources:
  • Mayoral
  • Federal

Location

Alice Austen Park, Staten Island

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 01/17/2025