Little Bay Parking Lot Reconstruction and Public Restroom Building Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a public restroom building and reconstruct the parking lot at Little Bay Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2005
Projected Completion Date: April 2012
Completion Date: May 2012

Procurement

Start Date: May 2012
Projected Completion Date: February 2013
Completion Date: January 2013

Construction

Start Date: March 2013
Projected Completion Date: September 2014
Completion Date: January 2016

Understand how we build parks.

Funding

Total Funding: $5,344,000
Funding Sources:
  • City Council
  • Federal
  • Mayoral

Location

Little Bay Park, Queens
Totten Avenue, Cross Island Parkway
Community Board: 07

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024