Ranaqua Exterior and HVAC Reconstruction
-
100% complete
-
0% complete
-
0% complete
This project will reconstruct the exterior façade and HVAC systems at Ranaqua in Bronx Park.
Project Notes
Project Update: Design is complete and permitting and legal review of the contract are in progress.
Project Timeline
Design
Assigned & Start Date: February 2023
Projected Completion Date:
August 2024
Completion Date:
August 2024
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Bronx Park, Bronx
1 Bronx River Parkway
Community Board: 06, 07, 11, 12
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024