Litchfield Villa Telecommunications Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install new telecommunications equipment at Litchfield Villa in Prospect Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2014
Projected Completion Date: March 2015
Completion Date: March 2015

Procurement

Start Date: April 2015
Projected Completion Date: September 2015
Completion Date: April 2015

Construction

Start Date: May 2015
Projected Completion Date: June 2015
Completion Date: June 2015

Understand how we build parks.

Funding

Total Funding: $100,000
Funding Source: Mayoral

Location

Prospect Park, Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024