Litchfield Villa Telecommunications Installation
-
100% complete
-
100% complete
-
100% complete
This project will install new telecommunications equipment at Litchfield Villa in Prospect Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2014
Projected Completion Date:
March 2015
Completion Date:
March 2015
Procurement
Start Date: April 2015
Projected Completion Date:
September 2015
Completion
Date:
April 2015
Construction
Start Date: May 2015
Projected Completion Date:
June 2015
Completion Date: June 2015
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Prospect Park, Brooklyn
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project